SumDU continues to systematically carry out work to eliminate consequences of the missile strike on 13 April 2025. Over the last week, a number of technical measures have been implemented in several academic buildings.
In Academic Building 2:
- 18 windows were repaired;
- An entrance door was replaced;
- Two double-leaf interior doors were installed;
- A report on inspection of structures was received; preparations began for ordering design work on conservation of a building section.
In Academic Building 3, three wooden arched windows were repaired and replaced.
In the Congress Center:
- 90 m² of roofing was repaired;
- A technical inspection report was received; an order for project documentation for the full building restoration within charitable funds is being prepared.
Besides, 40 m³ of construction debris was removed during the week, allowing access to the next stages of restoration.
SumDU keeps recording every step in the reconstruction process, maintaining openness to the public and partners. The work is being carried out in accordance with the plan and based on technical conclusions.